Unit 4 update

2018-06-16

Unit 4 was returned to service after a 105-day planned outage.


Unit 4 update

2018-06-15

A Bruce Power Boiler Safety Relief Valve in Unit 4 was opened in the early afternoon on June 15. Steam from the valve on the roof of the Bruce A generating station produced a sound that might have carried beyond … Read more


Unit 8 update

2018-05-09

Unit 8 was safely returned to service after a brief forced outage.


Unit 8 update

2018-05-06

Unit 8 was safely removed from service for a forced outage.


Unit 2 update

2018-03-23

Unit 2 was synchronized to the Independent Electricity System Operator (IESO) grid early March 23 following an 11-day forced outage.


Unit 2 update

2018-03-11

Unit 2 was safely removed from service on March 11 at  for a forced outage.


Unit 4 update

2018-03-04

Unit 4 at the Bruce A generating station was taken offline early Sunday morning due to an issue with one of the unit’s heat transport pumps. There was a release of heat transport water in a controlled area immediately adjacent … Read more


Unit 1 update

2018-02-28

Operations safely synchronized Unit 1 to the Independent Electricity System Operator (IESO) grid on Feb. 28, bringing Bruce A’s first planned outage of 2018 to a close.


Unit 8 update

2018-02-16

Unit 8 was returned to service after a 54 hour forced outage.


Page 2 of 3
Medical Isotopes - medical sterilization
Life-Extension and jobs in the trades
Electricity market and the price of power
Bruce Power Life-Extension Project boosting local economy

#NuclearAgainstRacism

We stand in solidarity with Black, Indigenous and People of Colour (BIPOC) communities across the world in the unquestionable proclamation that the lives of BIPOC Matter. 

Stay in touch

Sign up for our monthly eNewsletter

* indicates required